PWD (Building)

Last Updated on: March 23, 2022

DETAILS OF COMPLETED PROJECTS OF JORHAT DISTRICT UNDER P.W.D JORHAT BUILDING DIVISION

 

 

Sl No. Name of Schmes Tender Amount
(Rs.In L.)
F.W.O. No. & Date % of Physical Progress Remarks
 (Issue/Problems etc.)
1 2 3 4 5 6
UNDER GAD
1 Construction of Additional circuit House at Jorhat (Ancillary Works.) 25,93,545.00 SE(B)/JHT/(C/S)/S-417/14-15/497-01 dtd.28.05.14. 100% Work completed 
2 Construction of EAC's Quarter (R.C.C. Ground floor) 1 block 2 (two) units for Titabor Civil Sub-Division at Titabor. 50.49 SMC/3/2010/7-A dtd.26.02.10 100% Work completed. 
3 Integarated Office Complex for Titabor Sub-Division at Titabor.(Construction of RCC four storied office Building with provision of car parking at Ground floor)(Additional work  thereof). 59.35406 SMC/13/2015/9-A dtd.27.03.15 100% Work completed .
4 Construction of EAC's Quarter (R.C.C. Ground floor) 1 block 2 (two) units for Titabor Civil Sub-Division at Titabor(construction of Brick Boundary wall on North side, L= 86.00Rm) Group -A, (Additional work) 7.41900 IX/JBD/2017-18/Titabor/EAC/Qtr./B.Wall Deptt./JRT
/3230-A
dtd.13.12.17
100% Work completed.
5 Construction of EAC's Quarter (R.C.C. Ground floor) 1 block 2 (two) units for Titabor Civil Sub-Division at Titabor(construction of Brick Boundary wall on West & Froint side, L= 61.00Rm, Iron Gate and E. filling around the building) Group -B,(Additional work) 6.57385 IX/JBD/2017-18/Titabor/EAC/Qtr./B.Wall Deptt./JRT
/3229-A
dtd.13.12.17
100% Work completed.
UNDER CULTURAL AFFAIRS DEPTT.
6 Construction of Swargadeo Chaolung Siu-Ka-Pha Memorial cum Museum at Swargadeo Xhaolung Siu-Ka-Pha samanway Kshetra at Mohbondha, Jorhat. 735.84 ADP/825/2010/13-A dtd. 28.02.11 100% Work completed 
7 Making statue for Sargadeo Chaolung Siu-Ka-Pha on Memorial Building in the project site "Construction of Sawrgadeo - Chaolung Siu-Ka Pha Samannaya Kshetra. 24.0875 ADP/27/2013/09 dtd.01.03.14 100% Work completed.
8 Providing, Fixing, Testing & Commissioning of Rain Water Hardesting System with storage capacity 5000 ltr. In 2 (two) buildings of Swargadeo Chaolung Siu-ka-Pha Samanway Kshetra, Mohbandha, Jorhat (Excluding Civil Works). 5.75   100% Work completed.
9 Degine construction & Operation and Maintainane for a period of 6 (six) months of 3 Nos Bio-Toilets  of 50 user capacity at Swargadeo Chaolung SIU-KA-PHA Samannaya Kshetra at Mohbandha, Jorhat 5.49 CEB/MECH/5/2015/19 dtd. 09.10.15 100% Work completed.
UNTIED FUND
10 Infrastructure Development of Rajib Gandhi Sports Complex, Titabor in Jorhat 21.78189 IX/JBD/2015-16/Titabor/2729 dtd. 17.10.15 100% Work completed.
UNDER TECHNICAL EDUCATION DEPTT.
11 Modernization of Class Room Building and Main Building of Jorhat Engineering Collage, Jorhat under plan during 2015-16. 87.56067 T/BD/2016/5-A dtd.04.03.16 100% Work completed. 
UNDER JUDICIAL DEPARTMENT
12 Construction of Residence, RCC Two storied (G + 2 provision) building of Jorhat Bar Association, Jorhat 48.41304 Satyanarayan Lahoti 100% Work completed.
UNDER VETERINARY DEPTT.
13 Balance Work of Incomplete portion of Consrtruction of Veterinary Hospital (A/T & RCC Building)   at Marioni under RIDF-XVIII(package No.23)' 31.671 SE(B)/JHT/(C/S)/S-22/17-183612 dtd. 13.02.18 100% Work completed.
UNDER C.M'S SPECIAL SCHEME (PLAN)
14 Contruction of 2 (Two) class room for introduction of Comerce Stream in Jorhat District during 14-15 76.09975 BN/29/2015/B/24 dt. 11.01.16   Work completed and handed over.
(i) Bandar Chaliah High School, Titabor LAC (2 No. of class room) 100%
(ii) Rangajan High School, Titabor LAC (2 No. of class room) 100%
(iii) Titaram Bordoloi High School, Titabor LAC (2 No. of class room) 100%
(iv) Bahoibari High School, Jalukonibari, Titabor LAC (2 No. of class room) 100%
(v) Mihiram Saikia High School, Titabor LAC (2 No. of class room) 100%
15 Contruction of 2 (Two) class room and 1(one) Science Lab. for introduction of science stream in Jorhat District  during 2014-15  (package No.7)  47.55 BN/37/201511-A dtd.16.12.15    
Madhabdev Seminary High School, Titabor LAC (Class room - 2 Nos. & Sc.Lab-1No.). 100% Work completed.
Dhalasatra H.S. School, Titabor LAC (Class room - 2 Nos. & Sc.Lab-1No.). 100% Work completed.
UNDER RUSA
16 Infrastructure Grants to 21(tweenty one) Colleges of Assam under Rastriya Uchchatar Siksha Abhijan(RUSA) (Construction of Class Room at Jorhat Engineering College,Jorhat). 56.06933 CS/T/BD/20/2016/8-A dtd. 15.02.17 100% Work completd & handed over. 
17 construction of proposed RCC Ramp at Jorhat Engineering Collage. 19.81 SE(B)/JHT/(C/S)/S-12/17-18/2994-3001
DTD.10.10.17
100% Work completed.
UNDER MEDICAL EDUCATION DEPTT.
18 Construction of a temporary Biomedical Waste Storage at Jothat Medical college & Hospital Jorhat. 5.68712 IX/JBD/2018-19/JMC/JHTP/2340
dt.24.09.18
100% Work completed.
19 Package No.JKSHMC & H-1 " Construction of 100 bedded Boy's Hostel at Dr. JKS Homoeopathic College & Hospital, Jorhat under National AYUSH mission, Assam to the state Plan during the year 2015-16. (Including Internal Electrification work)". 73.76660 GMC.11/2016/20 dtd.28.10.2016 100% Work completed & handed over.
UNDER JAIL DEPARTMENT
20 Construction of Staff qtr at Open Air Jail, Jorhat under the scheme of modernisation of Prision administration during the year 2014-15 8.50126 SE(B)/JHT/(C/S)S-472/14-15/300-07 dtd. 23/04/15 100% Work completed.
21 Construction of Staff qtr at Central Jail (Qtr. No. 1) , Jorhat under the scheme of modernisation of Prision administration during the year 2014-15 8.50126 SE(B)/JHT/(C/S)S-475/14-15/309-15
dtd. 23/04/15
100% Work completed.
22 Construction of Staff qtr at Central Jail (Qtr. No. 2) , Jorhat under the scheme of modernisation of Prision administration during the year 2014-15 8.50126 SE(B)/JHT/(C/S)S-475A/14-15/357-64
dtd. 06/05/15
100% Work completed.
UNDER BORDER AREA DEVELOPMENT
23 Implementatin of Scheme under State Specific Fund for Upgradation of B.O.P and strengthening of road communication 2015-16 at No.2Naginijan in Jorhat District ( Package No BN-Bop-06 90,44,320 No BN/11/2017/20Dated Ghy 20-07-2017 100% Work completed 
24 Improvement Renovation of Assam Type Barrack at Gabharu B.O.P. under B.O.P. for 2018-19, Gr.No.(II) 4.98976 IX/JBD/2018-19/BOP/TITABOR/4164-66
DT.28.01.19
100% Work completed
25 Improvement Renovation of Assam Type Barrack at Dessoi Valley B.O.P. under B.O.P. for 2018-19, Gr.No.(II) 4.99566 IX/JBD/2018-19/BOP/TITABOR/4195-97
DT.30.01.19
100% Work completed
UNDER DAIRY DEVELOPMENT
26 Establishment of Milk Processing Plants Jorhat. 63.1794 ADP/02/2014/04-A
Dtd.28.02.14
100% Work completed. 

DETAILS OF ONGOING  PROJECTS OF JORHAT DISTRICT UNDER P.W.D JORHAT BUILDING DIVISION

Sl No. Name of Schmes Tender Amount
(Rs.In L.)
F.W.O. No. & Date % of Physical Progress Remarks
 (Issue/Problems etc.)
1 2 3 4 5 6
UNDER TECHINICAL EDUCATION DEPARTMENT
1 Construction of Auditorium at Jorhat Engineering Collage, Jorhat, Assam. 420.01 CE/REC/26/2017/34-A dtd.27.11.17 70% Work is in progress.
2 Construction of Women Hostel at P.O.W.I. Jorhat under Plan(CSS) during 2016-17 90.00 CS/T/BD/04/2017/15-A dtd.21.07.17 97% Work is in progress.
UNDER AQIS SCHEME
3 Construction of new hostel building for SC/ST students in H.R.H. The Prince of Wales Institute of Engineering & Technology, Jorhat under AICTE Govt of India sponsored AQIS Scheme. 157.93723 CS/T/BD/34/2018/9-A
dtd.21.08.18
70% Work is in progress.
4 Construction of new hostel building for SC/ST students Jorhat  Engineering College, Jorhat under AICTE Govt of India sponsored AQIS Scheme. 161.00 CS/T/BD/33/2018/13-A
dtd.20/08/18
56% Work is in progress.
UNTIED FUND
5 Development of Lachit Maidam, Holongapar under Untied Fund for the year 2016-17. 88.263 SE(B)/JHT/CS/S-7/17-18/3552-58 dtd.09.11.17 95% Work is in Progress.
6 Construction of Auditorium of Gumati Devi Girl's High School, Titabor 9.98096 IX/JBD/2015-16/UTF/Titabor/2729 dtd. 17.10.2015 64% Work stopped by the contractor.Notice served. 
7 Construction of Head Office of Small Tea Growers Association at Jorhat. 87.77262 SE(B)/JHT/CS/S-54/17-18/2455-60
dtd.09.07.18
85% Work  is in progress 
UNDER CULTURAL AFFAIRS DEPTT.
8 Construction of Swargadeo Chaolung Siu-Ka-Pha samannaya Kshetra at Mohbondha, Jorhat. 4582.90917 ADP/81/2012/pt/20 dtd18.02.13 96% Work  is in progress.
9 Construction of Swargadeo Chaolung Siu-Ka-Pha samannaya Kshetra at Mohbondha, Jorhat( Providiing Interior works of Museum Building, Memorial Building, Auditorium Building, Craft Centre, Administrative Building). 987.60628   60% Work is in progress.works could not be taken up due to non completion of civil works of the buildings.
10 Landscaping for Swargadeo Chaolung SIU-KA-PHA Samannaya Kshetra at Mohbandha, Jorhat 9.99923   83% Work stopped by the contractor as no fund is available.
11 Construction of Swargadeo Chaolung Siu-Ka-Pha samannaya Kshetra at Mohbondha, Jorhat(Construction of Ethnic Hut) 3.279 SE(B)/JHT/CS/S-46/18-19/7505-11
dtd.29.12.18
  Work  not yet started
12 Artisan village of Chaolung Siu-Ka-pha Memorial Building Mohbandha,Jorhat 63.85     Preliminary works started .
13 Construction of Auditorium of Tarajan Sanmilan,Jorhat during the year 2017-18 144.13795 ADP/56/2015/24-A dtd10.01.19 25% Work  is in progress 
14 Construction of Swargadeo Chaolung Siu-Ka-Pha samannaya Kshetra at Mohbondha, Jorhat(Installation of Fire Hydrant System) 39.99376 SE(B)/JHT/CS/S-42/18-19/7758-62
dtd.10.01.19
75% Work  is in progress.
15 Construction of Swargadeo Chaolung Siu-Ka-Pha samannaya Kshetra at Mohbondha, Jorhat(Construction of Sewage Treatment Plant)  10.00 SE(B)/JHT/CS/S-45/18-19/7513-19
dtd.29.12.18
  Preliminary works started .
16 Construction of Swargadeo Chaolung Siu-Ka-Pha samannaya Kshetra at Mohbondha, Jorhat(Construction of Outside Toilet Block ) 32.44056 SE(B)/JHT/CS/S-41/18-19/9397-402
dtd.07.03.19
  Preliminary works started .
17 Construction of Maidam of Chaolung Siu-Ka-pha memorial building, Mohbandha,Jorhat 10.00 SE(B)/JHT/CS/S-44/18-19/7262-68
dtd.18.12.18
  Preliminary works started .
UNDER MEDICAL EDUCATION DEPTT.
18 Retrofitting and Remrdial measures for Hospital Building at Jorhat Medical College Hospital, Jorhat , Package No. JMCH-HOSP 4687.66870 GMC 32/2013/Pt-I/18-A
dtd.28.01.19
15% Work is in progress.
 PRINTING & STATIONARY DEPARTMENT
19 Construction of Branch of Assam Govt. Press at Titabor. 354.2565 CS/T/BD/10/2014/21-A dtd.25.07.14 39% Work stopped by the contractor.Notice served .Additional estimate amounting to Rs 52,74,500.00 submitted.
UNDER EDUCATION DEPTT. 
20 Infrastructure Development of Jorhat Kendriya Mahavidyalaya under SPA (Plan) for the year 2014-15. 252.43 CS/T/BD/15/2015/12-A
dtd.02.07.15
86% Work is in progress.Revised estimate for balance work submitted.Demand submitted for Rs.24.98367(L).
UNDER DIRECTOR OF SPORTS
21 Construction of NCC Academy at Jorhat. 200.25022 ADP/67/2015/23-A dtd.19.01.17 77% Work is in progress . Notice served to the contractor for slow progress.
ACA/SPA
22 Repair/Renovation of 10(ten) old high performing Govt. H.S. Schools in the State under one time ACA during 2010-11 group No.:-II 349.39152 CS/CE/REC/07/2011/7 dtd. 20.07.11    
(ii) Infrastructure Development of Govt. Girl's H.S. & M.P. School Jorhat under ACA/SPA during 2010-11 100% Work completed & handed over.
(i) Infrastructure Development of Govt. Boy's H.S. & M.P. School Jorhat under ACA/SPA during 2010-11 94% Work stopped by the Contractor due to non payment of bill..Work will be resume by the contractor after receipt of payment.
23 Construction of Modern Fish Market at Jorhat under SPA during 2016-17. 396.59905 CS/T/BD/3/2018/28-A
dtd.29.11.18
  Work not yet started due to non submission of site for market.
UNDER BORDER AREA DEVELOPMENT
24 Implementatin of Scheme under State Specific Fund for Upgradation of B.O.P and strengthening of road communication 2015-16 at No.2 Mogroi village ( Package No BN-Bop-o6 90,74,102 No BN/11/2017 7% Work started .Presently construction for the temporary accommodation for Security Force is going on and security barrack is almost completed for accomodation of  force personnels and up-to-date 5% progress of original work was achieved till stopped the work. 
25 Implementatin of Scheme under construction of B.O.P. for Development Inter State Border Areas during 2014-15 at Huloonguri in Jorhat District.(Bn-BOP-B). 92.58006 BN/21/2014/20
dtd..23.03.18
  Required land for construction of B.O.P. was demarcated my concerned Revenue Circle, Mariani. Necessary formalities for handing over/ taking over of aforesaid land are not yet completed despite our several approaches to the concerned department.
The concerning circle officer of mariani revenue circle has been asked to hand over the site to concerning by the ADC(border)Jorhat.
UNDER VETERINARY DEPTT.
26 Construction of Veterinary Hospital Complex at Kalbari under RIDF- XVIII (Package No. 27.) 63.49363 ADP/85/2013/05-A
Dtd.16.07.14
80% Work forclose as per minites of metting held on 28.05.19. Incomplete final bill under process.
27 Construction of Veterinary Hospital Complex at  Teok (Rajabari) under RIDF- XVIII (Package No. 24.) 64.28 ADP/82/2013/05-A dtd.05.11.14 81% Work forclose as per minites of metting held on 28.05.19. Incomplete final bill under process.
28 Construction of Veterinary Hospital Complex at  Bolama under RIDF- XVIII (Package No. 29.) 63.495   96% Work is in progress. 
29 Construction of Veterinary Hospital Complex at Kumargaon  under RIDF- XVIII (Package No. 30.) 60.3203 ADP/88/2013/02-A
Dtd.03.05.14
70% Work is in progress. 
30 Balance Work of Incomplete portion of Consrtruction of Veterinary Hospital (A/T & RCC Building)   at Dholajan under RIDF-XVIII(package No.31)' 33.43683 ADP/89/2013/04-A
Dtd.03.03.14
70% Proposal for withdrawal of the work as per meeting held in 28 th may 2019.Work stopped by the contector
UNDER SOCIAL WELFARE  DEPTT.
31 Construction of Protective Home for Women along with Matrons Quarter at Titabor (Construction of Assam Type Protective Home for Women) 39.5992 SE(B)/JHT/CS/J/2013-14/10394-98 dt.30-11-13. 84% Work is in progress but slow.
32 Construction, Improvement/ Renovation works etc. for Observation Home, Jorhat for the year 2017-18(Construction, Improvement/ Renovation works) 20.00 SE(B)/JHT/(C/S)/S-50/18-19/7550-56 dt.01.01.19. 92% Work is in progress.
33 Construction, Improvement/ Renovation works etc. for Observation Home, Jorhat for the year 2017-18(Filter Unit with RCC Reservoir). 8.23 SE(B)/JHT/(C/S)/S-49/18-19/7558-65 dt.01.01.19. 75% Work is in progress
  Repairing/Renovation and up-gradation of the building of school for Hearing Impaired, Jorhat under SOPD-G for the year 2017-18. 52.87 SE(B)/JHT/©/S)/S-39/17-18/3176-82 dtd.02.08.18 85% Work is in progress
UNDER JUDICIAL DEPARTMENT
34 Provision of Railing in the Staircase, Parapet Wall at the top floor of class - III Judicial Quarter, Jorhat. 15.198 SE(B)/JHT/CS/S-14/17-18/3630-38 dtd 14.11.17 99% Work is in progress.
35 Construction of ADR  Centre at Jorhat in Jorhat District under Jorhat Building Division. 85.15969 BPM/45/2013/II-A dtd.12th Feb/2014 44% Work stopped..
36 Preparation and Construction of Approach road towards judicial quarter, Jorhat from K.B. Road. 8.21057 IX/JBD/2018-19/JUDICIAL/Qrt./JRT/416
dtd.25.07.18
80% Work is in progress..
UNDER SCIENCE AND TECHNOLOGY DEPARTMENT
37 Innovation Hub at Jorhat Science Centre & Planetarium, Jorhat. 74.4761 SE(B)/JHT/(C/S)/S-1/17-18/2537-45 dtd. 26.09.17 88% Work is in progress
UNDER NLCPR 
38 Mahapurush Sri Sri Madhabdeb Kalakhetra at Dhekiakhowa under NLCPR, Jorhat District 220.24448 CS/T/BD/15/2014/19
dtd.17.03.15
76% Work is in progress
UNDER JAIL DEPARTMENT
39 Construction of permanent sentry post in Central Jail , Jorhat    IX/JBD/2017-18/Central Jail/JRT/2873 dtd.13.11.17 85% Work is in progress. 
40 Construction of Proposed Assam Type Barrack for Female Inmates of Central Jail , Jorhat.  16.69 SE(B)/JHT/
(C/S)/S-21/18-19/4143-48
dtd. 04.09.18
70% Work is in progress.
UNDER SCHEME OF GAD
41 Construction of R.C.C.3 storied EAC's qtr.(Construction of 1st floor - 1 Block 2 Units) for Titabor Civil Sub-Division at Titabor in Jorhat District. 33.96786 SE(B)/JHT/(C/S)/S-2(A)/16-17/848-57 dtd.26.05.16 98% Work is in progress.
42 Construction of R.C.C.3 storied EAC's qtr.(Construction of second floor - 1 Block 2 Units) for Titabor Civil Sub-Division at Titabor in Jorhat District. 35.63 SE(B)/JHT/(C/S)/S-2(B)/16-17/1437-46
dtd.17.06.16
98% Work stopped by the contractor.
43 Construction of Gowdown/ Warehouse for proper storage EVM's and VVPATs in the 50 election district of Assam for the year 17-18 Group- C(DEO Titabor ). 208.43777 SMC/54/2018/5A
dtd..06.06.18
37% Work is in progress 
44 Construction of Gowdown/ Warehouse for proper storage EVM's and VVPATs in the 50 election district of Assam for the year 17-18 Group- B(DEO Jorhat). 173.38470 SMC/53/2018/5A
dtd..18.06.18
70% Work is in progress
UNDER FINANCE DEPARTMENT
45 Construction of Treasury Office Building at Jorhat G+ 2 Provision second floor Assam Type. 164.18161 CS/T/DD/06/2017/23
dtd.13.03.18
70% Work is in progress