Progress Report for Urban Development Projects

  • Progress Report for Urban Development Projects under Town & Country Planning, Jorhat (as nodal Agency) upto 31/07/2019

     

    Sl.No. Name of on-going Scheme/ programme Name of Implementing Agencies Allotted/Schematic (Amount in Lakhs) Unit
    /Target
    Progress/ Achievement, Amount Rs. in Lakhs Remarks
    (Issues/ Problems etc.)
    Physical Progress % of
    Physical
    Progress
    Financial Progress % of
    Financial
    Progress
    1 Truck terminus and Ware Housing Complex at Ailamukhia,Jorhat under 10% pool fund Jorhat Development Authority 1,017.00     85 716.14 70.42 *Work is in progress. UC submitted to the Govt. for the total released C/S & S/S. 3rd installment of C/S Rs 305.0 Lakhs yet to be released.
    2 Construction of Storm Water Drainage scheme at Jorhat Town  Under UIDSSMT Jorhat Municipal Board 1592.42 23.86 KM 19.680 KM 83.11 1305.07 81.96 * No progress since Oct/17.     ** U/C for 2nd installment of Central Share of Rs. 716.59 Lakhs will be submitting shortly
    3 Construction of Multistoried car parking cum city hall at Jorhat Town under NLCPR Jorhat Municipal Board 1051.33 - - 43 412.06 39.19 * No progress since July/18.    ** U/C for the released amount (C/S as well as S/S) had sent to the Directorate.
    4 Construction of Multiutility building at Jorhat Town under 10% pool fund Jorhat Municipal Board 1705 - - 15 233.89+58.83=292.72 13.72 * No Progress from the month April/15                                     ** U/C for the released amount (C/S) has been sent to the Directorate.                             *** Rs 58.83 Lakhs had been paid from interest.
    5 Construction Daily Market Complex at Teok Town under Infrastructure Development in other Towns Teok Municipal Board 30 - - 98 6 20 * Work is in progress.              ** U/C for Rs. 6.00 Lakhs (1st   installment released) had sent to the Directorate.
    6 Pradhan Mantri Awas Yojana (PMAY) Jorhat, Titabor & Teok Municipal Board - - - - - - *PMAY (U) BLC houses are being constructed in Jorhat, Titabar& Teok MB. Fund has transferred to 455 beneficiaries and 47 houses are almost completed.
    7 Preparation of Master Plans                                                                                                                     Jorhat,Titabor,Mariani & Majuli. *All maps of Jorhat Draft Revised Master Plan 2041 and Draft Master Plan Titabor 2041  have been prepared and send to the Directorate with preliminary reports and Detail Master Plan reports of the same will be send to the Directorate shortly.
    1. Revised Master Plan for Greater     Jorhat.  **Dag No. wise land use surveys have been carried out for Mariani with the help of revenue personnel of concerned Circle Offices. Base maps with Geo referencing have been completed for all those three towns.
    2. Draft Master Plan for Titabor.      ***All Cadastral maps for Majuli Revenue Circle are collected from DLR, Assam.
    3. Draft Master Plan for Mariani.
    4. Draft Regional Plan for Majuli

    *All maps of Jorhat Draft Revised Master Plan 2041 and Draft Master Plan Titabor 2041  have been prepared and send to the Directorate with preliminary reports and Detail Master Plan reports of the same will be send to the Directorate shortly.
     **Dag No. wise land use surveys have been carried out for Mariani with the help of revenue personnel of concerned Circle Offices. Base maps with Geo referencing have been completed for all those three towns.
    ***All Cadastral maps for Majuli Revenue Circle are collected from DLR, Assam.